Year |
Scope of Work |
Client |
 |
2011 |
Yme MOPU - Float off, mooring analysis and inshore assistance. |
Single Buoy Mooring |
 |
2011 |
Salvage under LOF - Refloat and Oil removal |
Eimskip |
 |
2010 |
Tow out and installation of self elevating platform Dutch sector. Mooring spread, vessels and engineering.
|
STP Offshore |
 |
2010 |
Gjøa Semi – Provision of tugs and planning for inshore float off, deck mating, sea trials and handover to offshore towage vessels |
Aker Solutions ASA |
|
2009 |
'Full City' - Oil recovery and refloat operation performed under "no cure - no pay" salvage contract. |
Smit Salvage /
Cosco Shipping |
 |
2009 |
Suspended tow and installation of bundle pipelines to Valhall field North Sea. |
Subsea 7 Norway |
 |
2009 |
Hywind Windmill – wet tow from Finland, inshore mooring and barge support. Towout and offshore hook up. |
Technip Offshore Norge AS |
 |
2008 |
Crete Cement – Oil recovery and refloating operation after grounding at Fagerstrand.
Contract performed in cooperation with Smit Salvage |
Kristian Gerhard Jebsen Skipsrederi AS |
 |
2007/08 |
Aker Drilling Deepwater Rigs– receipt of hull, manoeuvre to quay, sea trials and mooring operations |
Aker Stord |
|
2008 |
Tjuvholmen Development – undocking, transport and down ballasting of concrete modules for underwater car parking facility in Oslo |
Skanska |
 |
2008 |
Kittiwake Loading Buoy – cutting of anchor lines, towage to Vats and inshore mooring |
AF Decom AS |
|
2008 |
Provision of ‘BB Worker’ for offshore support for Spar Buoy deployment in US Gulf |
Heerema Marine Contractors |
 |
2007 |
Alvheim FPSO undocking, inshore mooring and offshore hook-up. Provision of vessels, towing master and operational planning. |
Marathon Petroleum Company |
 |
2007 |
Ekofisk Removal Project, barge transportation and planning of sea fastening, barge mooring. |
Heerema Marine Contractors |
 |
2006/ 2007/ 2008 |
Towage of Bjørvika concrete tunnel elements from Bergen to Oslo. Provision og tugs and procedures for the tows |
Skanska/ BAM |
 |
2006 |
Inshore installation of mooring lines and launching of Alvheim STP (Single Turret Production) buoy. Dry and wet towage and offshore hook up of STP buoy. Provision of marine personnel, tugs, procedures and towing masters. |
Technip Norge AS |
 |
2005 |
Deck mating of Kristin Platform. Provision of tugs and towing master |
Aker Stord |
 |
2005 |
Inn docking of process barge for the Hammerfest LNG plant. Provision of tugs and mooring equipment together with engineering and planning. |
Statoil ASA |